A report by the National Treasury has revealed that the proposed 419-kilometre Nairobi-Mombasa Expressway remains at the feasibility stage, more than two years after it was first approved as a privately initiated proposal (PIP).

According to the PPP Directorate, as of December 2025, Everstrong Capital, a U.S. infrastructure company hired to construct the expressway, had yet to officially begin the construction.

The project was first approved in December 2023 to proceed to the project development and feasibility study phase. However, the initial feasibility report submitted by the US-based firm failed to meet the required standards under the PPP Act of 2021.

As a result, the PPP Committee, in a decision made on July 2, 2025, resolved that the feasibility report should be abandoned in line with Section 43 of the law, effectively halting progress on the multi-billion-shilling project.

Everstrong Capital Senior Advisor, Kyle McCarter, submitting a 2300-page feasibility study report to KeNHA official for the construction of the Nairobi-Mombasa Expressway.
Everstrong Capital’s Senior Advisor, Kyle McCarter, submitting a 2300-page feasibility study report to KeNHA official for the construction of the Nairobi-Mombasa Expressway.

Despite the setback, the National Treasury left the door open for the project’s revival, and Everstrong Capital was allowed to resubmit a fresh feasibility study for a new determination.

“The Project Development Report (PDR) was finalised and submitted for approval. On July 2, 2025, it was determined that the PDR did not meet the relevant criteria and should be abandoned in accordance with Section 43(11) (c) of the PPP Act,” the report revealed.

“The proposal may, however, be resubmitted to the Committee for a fresh determination in line with Section 43 (12) of the PPP Act, 2021,” it added.

CS Mbadi’s Ultimatum to Everstrong Capital

The development comes barely a week after Treasury Cabinet Secretary John Mbadi gave Everstrong Capital a firm timeframe to meet the government’s strict compliance conditions.

Addressing the press on February 13, Mbadi told the U.S firm that the updated proposal must meet strict legal, technical, and financial benchmarks set by the Public-Private Partnership (PPP) Act of 2021.

The CS stated that if the revised proposal does not satisfy the set criteria, the government will turn it down and pursue a more cost-effective alternative, such as expanding the current Nairobi–Mombasa highway instead of building a new expressway.

“Everstrong Capital has submitted a revised development report. This is currently under review to determine if it meets the mandatory evaluation criteria,” Mbadi stated.

“If the proposal fails to pass this final stress test, KeNHA has the discretionary authority to declare the project abandoned with finality,” he added-Kenyans.co.ke.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

News

National Assembly dismisses claims Sacco Bill is being rushed through Parliament

Published

on

The National Assembly has dismissed reports that the Sacco Societies (Amendment) Bill, 2025, is being rushed through Parliament, saying the proposed law is still undergoing public participation.

Through infographics shared on Facebook on Tuesday, July 14, 2026, Parliament said misleading information had been circulating online about the Bill, formally known as the Sacco Societies (Amendment) Bill, National Assembly Bill No. 32 of 2025.

Bill was published in June 2025

The National Assembly said the Bill was published on June 30, 2025, and had remained under consideration for more than 12 months.

It rejected suggestions that lawmakers were fast-tracking the proposed amendments without allowing enough time for scrutiny.

According to Parliament, the lengthy period between the publication of the Bill and its current consideration shows that it is not being rushed.

Bill currently before the National Assembly committee

The Sacco Societies Amendment Bill is currently before the National Assembly’s Departmental Committee on Trade, Industry and Cooperatives.

The committee is conducting public participation and receiving views from members of the public and other stakeholders.

The submissions are expected to help the committee assess the proposed amendments before presenting its recommendations to the National Assembly.

What happens after public participation?

After the public participation process is concluded, the committee will prepare a report containing its findings and recommendations.

Parliament said the views submitted by members of the public and stakeholders could inform further amendments to the Bill.

The proposed legislation will then proceed to the National Assembly for consideration by MPs.

This means the Bill has not yet completed the legislative process and could still be amended based on the submissions received during public participation.

Bill will be forwarded to Senate

The National Assembly also clarified that the Bill will not proceed directly for presidential assent after being passed by MPs.

Because the proposed legislation concerns county governments, it will be forwarded to the Senate for consideration in accordance with the Constitution.

The Senate will be required to consider the Bill before it can complete the parliamentary process and be presented for presidential assent.

Parliament urged members of the public to rely on verified information about the Sacco Societies Amendment Bill instead of unconfirmed reports circulating online-PeopleDaily.Digital.

Continue Reading

News

Digital house-hunting platform bets on technology to reshape Nairobi’s rental market

Published

on

NAIROBI, Kenya, July 14 – A growing shift towards digital property searches is changing how Kenyans find rental homes, with real estate technology platform Reemio positioning itself as a solution to longstanding challenges.

This included fraudulent listings, costly house searches and limited market transparency.

As younger, tech-savvy consumers turn to online platforms to make purchasing decisions, the company says digitizing the rental process could improve efficiency for both tenants and landlords while lowering transaction costs.

“Our niche is to solve the problem of house hunting and also bring trust into that process. We use technology to connect renters and landlords,” said Kimani.

Kimani said the platform seeks to address inefficiencies that have traditionally made house hunting expensive and time-consuming.

Instead of physically visiting multiple properties, users can browse verified listings, take virtual tours, compare amenities and access information on additional costs such as water charges, electricity bills and service fees before scheduling physical viewings.

Beyond improving convenience for tenants, Reemio argues that technology can help landlords reduce marketing costs, shorten vacancy periods and reach a wider pool of prospective tenants, including Kenyans living abroad.

The company says its platform also generates market data that can help property owners and developers better understand evolving consumer preferences, although its long-term impact will depend on wider adoption of digital property platforms and continued investment in trustworthy online real estate marketplaces-Capitalfm.co.ke.

Continue Reading

News

ORPP edges two parties closer to joining Kenya’s political arena

Published

on

The Office of the Registrar of Political Parties (ORPP) has issued a notice for the provisional registration of two proposed political parties, opening a seven-day window for members of the public to lodge objections.

In a notice published by the Registrar of Political Parties and Chief Executive Officer J.C. Lorionokou, the ORPP announced that the Social Democratic Party of Kenya (SDP) and the People’s Alternative Voice (PAV) are in the process of being provisionally registered under Section 5(2)(a) of the Political Parties Act.

The ORPP, a State office established under Section 33 of the Political Parties Act and Article 260 of the Constitution, said its mandate includes registering and regulating political parties as well as administering the Political Parties Fund.

According to the notice, the Social Democratic Party of Kenya (SDP) has adopted pink, white and sky blue as its official party colours, with the slogan “Change – Mageuzi.” The party’s symbol is the acronym SDP enclosed inside a circle.

The party’s listed founder members are Nyangong’ Duncan Nyumbah, Omwandasi Jared Dishon and Kinyua Mary Wacuka.

The founders of PAV are listed as Odenyo John Fitzgerald Elly, Nyando Rachel Mmboga and Ali Hussein Kiplangat.

The Registrar said particulars of the two proposed political parties have been published on the ORPP website to facilitate public scrutiny as required by law.

Any person wishing to oppose the provisional registration of either party has seven days from the date of publication of the notice to submit objections either in writing or in person to the Office of the Registrar of Political Parties at Lion Place, Fourth Floor, Waiyaki Way at Karuna Close, Nairobi.

The provisional registration marks the first step in the legal process of establishing a political party in Kenya.

Kenya has 91 fully registered political parties. The ORPP’s updated register indicates that, as of January 2026, there were 91 parties that had met the legal requirements for full registration under the Political Parties Act-STAR.

Continue Reading

Trending